AWS Certified Advanced Networking - Specialty ANS-C01 Actual Exam Questions

80 Questions120 Minutes70% Passing Score▣ Updated: Sep 2026

Question 55 of 80

Single answer
Which set of steps should the network engineer follow in each AWS account to meet these requirements?
A1. In the Production account: Create a resource share in AWS Resource Access Manager for the transit gateway. Provide the Connectivity account ID. Enable the feature to allow external accounts 2. In the Connectivity account: Accept the resource. 3. In the Connectivity account: Create an attachment to the VPC subnets. 4. In the Production account: Accept the attachment. Associate a route table with the attachment.
B1. In the Production account: Create a resource share in AWS Resource Access Manager for the VPC subnets. Provide the Connectivity account ID. Enable the feature to allow external accounts. 2. In the Connectivity account: Accept the resource. 3. In the Production account: Create an attachment on the transit gateway to the VPC subnets. 4. In the Connectivity account: Accept the attachment. Associate a route table with the attachment.
C1. In the Connectivity account: Create a resource share in AWS Resource Access Manager for the VPC subnets. Provide the Production account ID. Enable the feature to allow external accounts. 2. In the Production account: Accept the resource. 3. In the Connectivity account: Create an attachment on the transit gateway to the VPC subnets. 4. In the Production account: Accept the attachment. Associate a route table with the attachment.
D1. In the Connectivity account: Create a resource share in AWS Resource Access Manager for the transit gateway. Provide the Production account ID Enable the feature to allow external accounts. 2. In the Production account: Accept the resource. 3. In the Production account: Create an attachment to the VPC subnets. 4. In the Connectivity account: Accept the attachment. Associate a route table with the attachment.
Correct Answer: D

1. In the Connectivity account: Create a resource share in AWS Resource Access Manager for the transit gateway. Provide the Production account ID Enable the feature to allow external accounts. 2. In the Production account: Accept the resource. 3. In the Production account: Create an attachment to the VPC subnets. 4. In the Connectivity account: Accept the attachment. Associate a route table with the attachment.

Explanation

The correct answer is highlighted above. Review the wording carefully, then use the next question to continue building your understanding of AWS certification topics.