Question 217 of 284
Single answerYour company runs one batch process in an on-premises server that takes around 30 hours to complete. The task runs monthly, can be performed offline, and must be restarted if interrupted. You want to migrate this workload to the cloud while minimizing cost. What should you do?
ACreate an Instance Template with Spot VMs On. Create a Managed Instance Group from the template and adjust Target CPU Utilization. Migrate the workload.
✓BMigrate the workload to a Compute Engine VM. Start and stop the instance as needed.
CMigrate the workload to a Google Kubernetes Engine cluster with Spot nodes.
DMigrate the workload to a Compute Engine Spot VM.
✓
Correct Answer: B
Migrate the workload to a Compute Engine VM. Start and stop the instance as needed.
▥