Question 30 of 315
Choose 2A lead engineer wrote a custom tool that deploys virtual machines in the legacy data center. He wants to migrate the custom tool to the new cloud environment.
You want to advocate for the adoption of Google Cloud Deployment Manager.
What are two business risks of migrating to Cloud Deployment Manager? (Choose two.)
What are two business risks of migrating to Cloud Deployment Manager? (Choose two.)
ACloud Deployment Manager uses Python
✓BCloud Deployment Manager APIs could be deprecated in the future
✓CCloud Deployment Manager is unfamiliar to the company's engineers
DCloud Deployment Manager requires a Google APIs service account to run
ECloud Deployment Manager can be used to permanently delete cloud resources
FCloud Deployment Manager only supports automation of Google Cloud resources
✓
Correct Answer: B, C
Cloud Deployment Manager APIs could be deprecated in the future
▥
Explanation
The correct answer is highlighted above. Review the wording carefully, then use the next question to continue building your understanding of Google certification topics.