Google Professional Cloud DevOps Engineer Exam

202 Questions120 Minutes70% Passing Score▣ Updated: Sep 2026

Question 145 of 202

Single answer

You recently noticed that one of your services has exceeded the error budget for the current rolling window period. Your company's product team is about to launch a new feature. You want to follow Site Reliability Engineering (SRE) practices. What should you do?

A

A. Notify the team about the lack of error budget and ensure that all their tests are successful so the launch will not further risk the error budget

B

B. Notify the team that their error budget is used up. Negotiate with the team for a launch freeze or tolerate a slightly worse user experience.

C

C. Escalate the situation and request additional error budget.

D

D. Look through other metrics related to the product and find SLOs with remaining error budget. Reallocate the error budgets and allow the feature launch.

Correct Answer: A

<p>B. Notify the team that their error budget is used up. Negotiate with the team for a launch freeze or tolerate a slightly worse user experience.</p>

Explanation

The correct answer is highlighted above. Review the wording carefully, then use the next question to continue building your understanding of Google certification topics.