Question 72 of 139
Single answerYou need to migrate a 1 TB PostgreSQL database from a Compute Engine VM to Cloud SQL for PostgreSQL. You want to ensure that there is minimal downtime during the migration. What should you do?
AExport the data from the existing database, and load the data into a new Cloud SQL database.
BUse Migrate for Compute Engine to complete the migration.
CUse Datastream to complete the migration.
✓DUse Database Migration Service to complete the migration.
✓
Correct Answer: D
Use Database Migration Service to complete the migration.
▥
Explanation
The correct answer is highlighted above. Review the wording carefully, then use the next question to continue building your understanding of Google certification topics.