Question 76 of 139

Single answer
Your company is shutting down their on-premises data center and migrating their Oracle databases using Oracle Real Application Clusters (RAC) to Google Cloud. You want minimal to no changes to the applications during the database migration. What should you do?
AMigrate the Oracle databases to Cloud Spanner.
BMigrate the Oracle databases to Compute Engine.
CMigrate the Oracle databases to Cloud SQL.
DMigrate the Oracle databases to Bare Metal Solution for Oracle.
Correct Answer: D

Migrate the Oracle databases to Bare Metal Solution for Oracle.

Explanation

The correct answer is highlighted above. Review the wording carefully, then use the next question to continue building your understanding of Google certification topics.